- 20 Burdap Dr Mount Evelyn 3796
Upgrade and Modernisation – Stage 4
Start
Q4 2020Planning
Design
Construction
Finish
Q2 2025
The above dates are forecast only and subject to change.
About the project
We delivered the last stage of the school's master plan, which included the construction of the senior years learning building and additional administration space.
Funding
In the 2020–21 State Budget, the school received $8.926 million.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation – Stage 3
Start
Q2 2020Planning
Design
Construction
Finish
Q1 2024
The above dates are forecast only and subject to change.
About the project
We built a middle school building and specialist learning spaces. The new facilities include classrooms, a library, TV production studio, digital media, food technology, fitness centre, performance and multiple-purpose room, and an art room.
Funding
In 2020, the school received $10 million to deliver the next stage of the masterplan.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation – Stage 2
Start
Q2 2019Planning
Design
Construction
Finish
Q1 2021
The above dates are forecast only and subject to change.
About the project
We built a new junior learning building with 4 general purpose classrooms, a laundry, bathrooms, office space, a sick bay and outdoor areas.
We also removed an old relocatable building in poor condition.
Funding
In the 2019–20 State Budget, the school received $3.451 million.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation – Stage 1
Start
Planning
Design
Construction
Finish
Q4 2019
The above dates are forecast only and subject to change.
About the project
We replaced the relocatable administration building with a new administration building. The new building includes a general office, homecrafts café, interview room, staff offices and staff lounge.
Funding
In the 2017–18 State Budget, $500,000 was allocated to the school.
Funding type
- Upgrade and Modernisation
Updated