- 2370 Warburton Hwy Yarra Junction 3797
Upgrade and Modernisation
Start
Planning
Design
Construction
Finish
Q1 2018
The above dates are forecast only and subject to change.
About the project
We built a new senior block, expanding the administration facilities, refurbishing the music block and landscaping the grounds at Yarra Junction Primary School.
Funding
In the 2015–16 State Budget, $2 million was allocated to the school.
Funding type
- Upgrade and Modernisation
Minor Capital Works Fund
Start
Q4 2020Planning
Design
Construction
Finish
Q3 2021
The above dates are forecast only and subject to change.
About the project
We helped the school to redevelop the existing outdoor netball court to improve safety and ease of use.
Funding
In the 2020 Minor Capital Works Fund the school was allocated $63,120.
Funding type
- Minor Capital Works Fund
Updated