- 32 High St Bannockburn 3331
Building Fund for Non-Government Schools – Catholic
Start
Q3 2024Planning
Design
Construction
Finish
Q1 2027
The above dates are forecast only and subject to change.
About the project
We are helping the school complete the senior building with 4 new general learning areas. The school will also gain a new visual arts building.
Funding
In the Building Fund for Non-Government Schools - Catholic stream, the school received $2.4 million.
Funding type
- Building Fund for Non-Government Schools
Non-Government Schools Capital Fund - 2019-20
Start
Q4 2019Planning
Design
Construction
Finish
Q1 2022
The above dates are forecast only and subject to change.
About the project
We supported the school to continue to convert Bannockburn Primary School into the new St Mary MacKillop Catholic Primary School.
Funding
As part of the 2019–20 capital funding program for non-government schools, $3,510,000 has been allocated to the school.
Funding type
- Non-Government Schools Capital Fund
Non-Government Schools Capital Fund
Start
Planning
Design
Construction
Finish
Q2 2019
The above dates are forecast only and subject to change.
About the project
The existing state school was refurbished to create a new Catholic primary school.
Funding
$1,000,000 was allocated to the school as part of Round 3 of the Non-Government Schools Grants Program
Funding type
- Non-Government Schools Capital Fund
Updated