- 67 The Esplanade Maribyrnong 3032
Building Fund for Non-Government Schools – Catholic
Start
Q2 2023Planning
Design
Construction
Finish
Q2 2026
The above dates are forecast only and subject to change.
About the project
We helped the school build 3 new general learning areas. The project also included:
- refurbishment of 2 existing learning areas
- upgrades to the playground
- landscaping works
- demolition and relocation of demountable buildings.
Funding
Under the 2023–24 capital funding program for non-government schools, the school received $2.6 million.
Funding type
- Building Fund for Non-Government Schools
Non-Government Schools Capital Fund – 2021–22
Start
Q3 2021Planning
Design
Construction
Finish
Q2 2023
The above dates are forecast only and subject to change.
About the project
We helped the school build:
- 6 general learning areas
- a science, technology, engineering and mathematics (STEM) resource centre
- a presentation space
- an ICT support workshop
- an administration area.
Funding
Under the 2021–22 capital funding program for non-government schools, the school received $3 million.
Funding type
- Non-Government Schools Capital Fund
Updated