- 81 Hallifax St Seaford 3198
Upgrade and Modernisation – next stage
Start
Q2 2023Planning
Design
Construction
Finish
Q4 2026
The above dates are forecast only and subject to change.
About the project
We are continuing to upgrade and modernise this school. We will complete the next stage of planned improvements.
Funding
In the 2023-24 State Budget the school shared in $24 million allocated for planning. In the 2024-25 State Budget, total project funding of $18.2 million was announced.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation
Start
Planning
Design
Construction
Finish
Q2 2019
The above dates are forecast only and subject to change.
About the project
We constructed a competition-grade gymnasium and performing arts centre at Seaford North Primary School.
Funding
In the 2017–18 State Budget, $5 million was allocated to the school. In the 2016–17 State Budget, $12 million was allocated to schools across the state for planning. This included funding for Seaford North Primary School.
Funding type
- Upgrade and Modernisation
Updated