Rutherglen High School

Location
40 Sheridans Bridge Road Rutherglen 3685

Upgrade and Modernisation

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q3 2018

The above dates are forecast only and subject to change.

About the project

We completed building a STEM Centre at Rutherglen High School in 2018. 

Funding

In the 2016-17 State Budget, $1.6 million has been allocated to the school.

Funding type

  • Upgrade and Modernisation

Minor Capital Works Fund

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2024

The above dates are forecast only and subject to change.

About the project

We refurbished the toilets in the main wing of the school to improve amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.

Funding

In the 2022-23 State Budget the project received $496,397 from the Minor Capital Works Fund.

Funding type

  • Minor Capital Works Fund

Updated