- Bedford Rd Ringwood 3134
Upgrade and Modernisation - Stage 3
Start
Q4 2020Planning
Design
Construction
Finish
Q2 2024
The above dates are forecast only and subject to change.
About the project
We built on the major upgrades delivered to Ringwood Secondary students since 2017, by constructing a new STEAM (science, technology, engineering, arts and mathematics) building and canteen.
Funding
In the 2020–21 State Budget, the school received $14.735 million.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation - Stage 2
Start
Q2 2018Planning
Design
Construction
Finish
Q4 2020
The above dates are forecast only and subject to change.
About the project
We completed Stage 2 of the school's upgrade, building a two-storey senior learning centre. This features classrooms, a collaborative central space, break-out areas and a VCE centre. The first floor also connects to the upper level of the Workshop and Trades Building.
Funding
In the 2018–19 State Budget $5.5 million was allocated to the school.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation - Stage 1
Start
Planning
Design
Construction
Finish
Q3 2017
The above dates are forecast only and subject to change.
About the project
We completely redeveloped the school, including constructing a new Junior School building, replacing 11 relocatables with permanent classrooms, refurbishing the library, and reconfiguring the car park.
The Maroondah Education Plan includes Ringwood Secondary College's redevelopment, a stadium for Norwood Secondary College, a performing arts centre for Mullum Primary School, and the consolidation of Melba College's two campuses onto one site.
Funding
In the 2014–15 State Budget, $2.2 million was allocated to the school. The school also received $357,727 in planned maintenance funding. In the 2015–16 State Budget, $5 million was allocated to the school.
Funding type
- Upgrade and Modernisation
Updated