- 56B Hotham Street Preston 3072
Upgrade and Modernisation
Start
Q2 2020Planning
Design
Construction
Finish
Q4 2023
The above dates are forecast only and subject to change.
About the project
We built a three-storey learning and administration building. The new building includes:
- indoor and outdoor areas for general learning
- specialist learning spaces for science and technology
- staff and administration areas.
We provided new outdoor play areas and completed landscaping as part of this project.
The new facilities allow the school to offer places for an extra 200 local students.
Funding
In 2020, the school received at least $14.63 million, which is a share in $130.1 million from the Established Areas Program.
Funding type
- Upgrade and Modernisation
Updated