Parktone Primary School

Location
Robert St Parkdale 3195

Upgrade and Modernisation - Next Stage

  • Start

    Q4 2020
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2022

The above dates are forecast only and subject to change.

About the project

We upgraded the school by building a new library. We also moved the relocatable buildings.

Funding

In the 2020–21 State Budget, the school received $3.466 million.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q1 2019

The above dates are forecast only and subject to change.

About the project

We constructed classrooms and a new multi-purpose hall. ​

Funding

In the 2016–17 State Budget, $4 million was allocated to the school.

Funding type

  • Upgrade and Modernisation

Minor Capital Works Fund

  • Start

    Q4 2020
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2022

The above dates are forecast only and subject to change.

About the project

We installed acoustic materials in the stadium.

Funding

In the 2020 Minor Capital Works Fund, the school was allocated $377,165.

Funding type

  • Minor Capital Works Fund

Inclusive Schools Fund

  • Start

    Q4 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2020

The above dates are forecast only and subject to change.

About the project

We built a student lounge with sensory equipment, including a crash mat, interactive liquid tiles, blinds and dimmer lighting.

Funding

In 2018, $195,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.

Funding type

  • Inclusive Schools Fund

Updated