- 16-18 O'Brien Street Mooroopna 3629
Schools Upgrade Fund
Start
Q2 2024Planning
Design
Construction
Finish
Q2 2026
The above dates are forecast only and subject to change.
About the project
We are upgrading the outdoor area on the east side of the school's art and administrative building. This includes building a new covered walkway. We are also refurbishing the internal corridor.
Funding
The project received $1,021,936 from Round 2 of the Australian Government Schools Upgrade Fund.
Funding type
- Australian Government Schools Upgrade Fund
Inclusive Schools Fund - Round 9
Start
Q4 2023Planning
Design
Construction
Finish
Q1 2025
The above dates are forecast only and subject to change.
About the project
We are building an outdoor inclusive learning space. It will give children of all abilities new ways to socialise, develop and learn through play.
Funding
In Round 9 of the Inclusive Schools Fund, the project received $229,914
Funding type
- Inclusive Schools Fund