Mildura West Primary School

Location
219-227 Ninth St Mildura 3500

Minor Capital Works Fund

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2023

The above dates are forecast only and subject to change.

About the project

We refurbished the school's toilets to improve amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund. A program for small building projects that make a big difference in our schools.

Funding

In the 2022–23 State Budget the project received $499,397 from the Minor Capital Works Fund.

Funding type

  • Minor Capital Works Fund

Upgrade and Modernisation

  • Start

    Q2 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2020

The above dates are forecast only and subject to change.

About the project

We upgraded and refurbished facilities at the school in 3 phases.

In phase one, we built a new learning hub with new classrooms, refurbished Block A and provided new classroom areas and breakout spaces.

In phase 2, we created a new covered outdoor learning area.

In the final phase, we demolished a multipurpose building to allow for the development of landscaped outdoor space between the library and Block D.

Basic maintenance works were also carried out across all 3 phases.

Funding

In the 2018–19 State Budget $1.8 million was allocated to the school.

Funding type

  • Upgrade and Modernisation

Updated