- 189 Wollaston Road Warrnambool 3280
Minor Capital Works Fund
Start
Q2 2022Planning
Design
Construction
Finish
Q4 2024
The above dates are forecast only and subject to change.
About the project
We are constructing a new accessible toilet adjacent to the school's oval and basketball courts. This work is supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.
Funding
In the 2022-23 State Budget the project received $112,397 from the Minor Capital Works Fund.
Funding type
- Minor Capital Works Fund
Upgrade and Modernisation
Start
Q2 2018Planning
Design
Construction
Finish
Q1 2020
The above dates are forecast only and subject to change.
About the project
We completely rebuilt this school (previously known as Warrnambool Special Developmental School), giving students and staff the modern facilities they need.
The school consulted students, teachers and the local community about needs. This helped to identify what building works were needed. The curriculum needs of the school, as well as their future ambitions, were also considered as part of this process.
Funding
In the 2015-16 State Budget, $5 million was allocated to the school. The Government has subsequently announced $14.6 million in additional funding.
Funding type
- Upgrade and Modernisation
Updated