Lorne P-12 College

Location
15 Grove Rd Lorne 3232

Upgrade and Modernisation

  • Start

    Q4 2020
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2023

The above dates are forecast only and subject to change.

About the project

We upgraded and modernised the school. This included demolishing Block A and Block D, and constructing a new specialist building that included visual arts, textiles, media arts, visual communications and food technology learning spaces. We also added accessible pathways.

Funding

In the 2020–21 State Budget, the school received $8.972 million.

Funding type

  • Upgrade and Modernisation

Inclusive Schools Fund

  • Start

    Q4 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2019

The above dates are forecast only and subject to change.

About the project

We redesigned the school library to make it an inviting and inclusive learning space. The library area can now be used during class times, play times and for voluntary use.

Funding

In 2018, $200,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.

Funding type

  • Inclusive Schools Fund

Updated