Lang Lang Primary School

Location
52 Westernport Rd Lang Lang 3984

Capital Works Fund

  • Start

    Q4 2025
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2026

The above dates are forecast only and subject to change.

About the project

We refurbished the school’s running track. This improves the quality, making it safer and allowing students of all abilities to play, learn and develop together.

Our Capital Works Fund supported this work. It provides funding for smaller building projects that make a big difference in our schools.

Funding

Through the 2025–26 round of the Capital Works Fund, the project received $34,998.

Funding type

  • Capital Works Fund

Minor Capital Works Fund – Round 2

  • Start

    Q4 2021
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2023

The above dates are forecast only and subject to change.

About the project

We refurbished the student bathroom to improve amenity, cleanliness and hygiene.

Funding

In Round 2 of the Minor Capital Works Fund, the project received $359,127.

Funding type

  • Minor Capital Works Fund

Upgrade and Modernisation

  • Start

    Q2 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2022

The above dates are forecast only and subject to change.

About the project

We transformed the school's old classrooms so that students and staff have modern learning environments.

Funding

In the 2019–20 State Budget, the school received $153,800. In 2020, the school received $1.384 million.

Funding type

  • Upgrade and Modernisation

Updated