- Murphy St Brighton 3186
Inclusive Schools Fund - Round 6
Start
Q2 2021Planning
Design
Construction
Finish
Q4 2024
The above dates are forecast only and subject to change.
About the project
We are building an indoor inclusive learning space, including new sensory equipment.
Funding
In Round 6 of the Inclusive Schools Fund, this project received $200,000.
Funding type
- Inclusive Schools Fund
Minor Capital Works Fund – hall and gym toilets refurbishment
Start
Q2 2022Planning
Design
Construction
Finish
Q2 2024
The above dates are forecast only and subject to change.
About the project
We partially refurbished the hall and gym student toilets to improve amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.
Funding
In the 2022–23 State Budget the project received $469,127 from the Minor Capital Works Fund.
Funding type
- Minor Capital Works Fund
Minor Capital Works Fund
Start
Q4 2020Planning
Design
Construction
Finish
Q3 2023
The above dates are forecast only and subject to change.
About the project
We upgraded and resurfaced the oval.
Funding
In the 2020 Minor Capital Works Fund, the school was allocated $324,165.
Funding type
- Minor Capital Works Fund