Diggers Rest Primary School

Location
Plumpton Rd Diggers Rest 3427

Upgrade and Modernisation – Community Hub

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2025

The above dates are forecast only and subject to change.

About the project

We are modernising the school to give students better learning opportunities. In this significant upgrade, we will build a new school community hub and learning centre.

Funding

In the 2022–23 State Budget, this school received $13.443 million.

Funding type

  • Upgrade and Modernisation

Minor Capital Works Fund

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2023

The above dates are forecast only and subject to change.

About the project

We refurbished the senior student toilet block. This has improved amenities, cleanliness and hygiene.

Funding

In the 2022–23 State Budget the project received $237,669 from the Minor Capital Works Fund.

Funding type

  • Minor Capital Works Fund

Upgrade and Modernisation - Next Stage

  • Start

    Q4 2020
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2023

The above dates are forecast only and subject to change.

About the project

We continued to upgrade and modernise the school. These works included the administration block.

Funding

In the 2020–21 State Budget, the school received $3.204 million.

Funding type

  • Upgrade and Modernisation

Inclusive Schools Fund

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q1 2018

The above dates are forecast only and subject to change.

About the project

We created engaging nature-based learning stations in the outside spaces of classrooms.

These facilities include a sensory garden, a rock seating auditorium, a games zone, and log seating. Each space accommodates the sensory and withdrawal needs of students.

Funding

In Round 2 of the Inclusive Schools Fund, $181,500 was allocated to the school.

Funding type

  • Inclusive Schools Fund

Upgrade and Modernisation

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q2 2018

The above dates are forecast only and subject to change.

About the project

We updated and refurbished classrooms and facilities in poor condition to improve standards across the school, ensuring the school has the learning facilities it requires to deliver modern education.

Funding

In the 2017–18 State Budget, $151,000 was allocated to the school.

Funding type

  • Upgrade and Modernisation

Updated