- 21 Nelson St Bacchus Marsh 3340
Upgrade and Modernisation
- StartQ2 2022
- Planning
- Design
- Construction
- FinishQ2 2025
The above dates are forecast only and subject to change.
About the project
We modernised the school to give students better learning opportunities.
We:
- built a new administration building at the front of the school to create a more welcoming entrance
- upgraded and extended one of the learning blocks to form a new learning community
- partly demolished the main block, including the arts, staff and admin areas
- moved one relocatable building and demolished another
- landscaped to improve the outdoor areas.
Funding
In the 2022–23 State Budget, this school received $10.678 million.
Funding type
- Upgrade and Modernisation
Inclusive Schools Fund
- StartQ4 2018
- Planning
- Design
- Construction
- FinishQ3 2019
The above dates are forecast only and subject to change.
About the project
We built a new outdoor learning area with a classroom space, a rock-seating amphitheatre, fitness trail and sensory garden. We also installed a spider web climber, a jungle square, a trampoline and a moving balance beam.
Funding
In 2018, $200,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.
Funding type
- Inclusive Schools Fund
Updated