- 25-47 Warkil St Cobram 3644
Minor Capital Works Fund
Start
Q2 2022Planning
Design
Construction
Finish
Q1 2024
The above dates are forecast only and subject to change.
About the project
We refurbished the staff and student toilets in the school's technical wing to improve amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.
Funding
In the 2022–23 State Budget the project received $499,397 from the Minor Capital Works Fund.
Funding type
- Minor Capital Works Fund
Permanent Modular School Buildings Program
Start
Q2 2019Planning
Design
Construction
Finish
Q4 2020
The above dates are forecast only and subject to change.
About the project
We replaced an older building containing asbestos with a new architecturally-designed permanent modular building.
Our modular facilities require less time for planning and construction, resulting in reduced disruption to students, staff and teaching programs. They are sustainable and innovatively designed, with a comparable lifespan to bricks and mortar structures. The school is benefitting from the Permanent Modular School Buildings Program.
Funding
In the 2019–20 State Budget, the school received $3.392 million through the Permanent Modular School Buildings Program.
Funding type
- Permanent Modular School Buildings Program
Updated