Upgrade and Modernisation - Next Stage
Start
Q4 2020Planning
Design
Construction
Finish
Q4 2023
The above dates are forecast only and subject to change.
About the project
We modernised the school. We continued the work we completed in 2019 and built new classrooms and a food technology centre.
Funding
From the 2020–21 Infrastructure Planning and Acceleration fund, the school was allocated $1.019 million in planning funding. In the 2020–21 State Budget, the school received $9.175 million.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation - Stage 1
Start
Q2 2016Planning
Design
Construction
Finish
Q1 2019
The above dates are forecast only and subject to change.
About the project
We delivered a new administration and multipurpose hall building.
Funding
In the 2016–17 State Budget, $12 million was allocated to schools across the state for planning. This includes funding for Bundoora Primary School. In the 2017–18 State Budget, $3.5 million was allocated to the school.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation - Stage 2
Start
Q2 2018Planning
Design
Construction
Finish
Q4 2019
The above dates are forecast only and subject to change.
About the project
Stage 2 works at the school delivered a new STEAM (Science, Technology, Engineering, Art, and Mathematics) and Library Centre.
Funding
In the 2018–19 State Budget $2.707 million was allocated to the school.
Funding type
- Upgrade and Modernisation