Bundarra Primary School

Location
Cnr Fawthrop & Edgar St Portland 3305

Find out more about the kindergarten we're building at Bundarra Primary School.

Inclusive Schools Fund - Round 6

  • Start

    Q2 2021
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2023

The above dates are forecast only and subject to change.

About the project

We built an outdoor learning space. It is an inclusive, landscaped environment and includes a yarning circle.

Funding

In Round 6 of the Inclusive Schools Fund, this project received $200,000.

Funding type

  • Inclusive Schools Fund

Inclusive Schools Fund - Round 4

  • Start

    Q4 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2019

The above dates are forecast only and subject to change.

About the project

We built a sensory play space, with musical activities, sand and water play, an access spinner, roller table, rockin’ robin (i.e. an egg chair) and visual stimuli that will continue to improve the curriculum for children with special needs.

Funding

In 2018, $164,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.

Funding type

  • Inclusive Schools Fund

Updated