- 185 Surrey Road Blackburn 3130
Minor Capital Works Fund
Start
Q4 2020Planning
Design
Construction
Finish
Q2 2021
The above dates are forecast only and subject to change.
About the project
We replaced the toilets with new toilet blocks.
Funding
In the 2020 Minor Capital Works Fund, the school was allocated $283,912.
Funding type
- Minor Capital Works Fund
School Pride and Sports Fund
Start
Q1 2020Planning
Design
Construction
Finish
Q3 2020
The above dates are forecast only and subject to change.
About the project
We supported the school with minor upgrades, including drainage.
Funding
From the 2019–20 School Pride and Sports Fund the school received $220,557.
Funding type
- School Pride and Sports Fund