- 12-14 Florence St Blackburn 3130
Minor Capital Works Fund
Start
Q4 2020Planning
Design
Construction
Finish
Q4 2023
The above dates are forecast only and subject to change.
About the project
We built an outdoor nature play space to encourage play within a natural environment.
Funding
In the 2020 Minor Capital Works Fund, the school was allocated $321,125.
Funding type
- Minor Capital Works Fund
Inclusive Schools Fund
Start
Q4 2018Planning
Design
Construction
Finish
Q2 2020
The above dates are forecast only and subject to change.
About the project
We built a multi-sensory playground with accessible equipment, such as swinging steps, a balance beam, chimes and a shade structure.
Funding
In 2018, $200,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.
Funding type
- Inclusive Schools Fund