- 270 Sheffield Rd Montrose 3765
Upgrade and Modernisation
Start
Q4 2020Planning
Design
Construction
Finish
Q3 2024
The above dates are forecast only and subject to change.
About the project
We built a new 2-level education building. The new building includes 7 general classrooms, a kitchen garden cooking space, a science and technology room and a new art room. The project also included landscaping.
Funding
In the 2020–21 State Budget, the school received $7.811 million.
Funding type
- Upgrade and Modernisation
School Pride and Sports Fund
Start
Q2 2017Planning
Design
Construction
Finish
Q4 2018
The above dates are forecast only and subject to change.
About the project
We redeveloped the front entry of the school. We created a covered area at the front entry to provide a sun safe area for play and a shelter for students as they wait for buses or to be picked up after school.
Funding
In 2017–18 the school received $429,000 in Round 3 of the School Pride and Sports Fund.
Funding type
- School Pride and Sports Fund
Updated