Bentleigh Secondary College

Location
Vivien St Bentleigh East 3165

Upgrade and Modernisation – performing arts centre

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2024

The above dates are forecast only and subject to change.

About the project

We modernised the school to give students better learning opportunities. In this significant upgrade, we built a new performing arts centre.

Funding

In the 2020–21 State Budget, the school received $50,000 for planning. In the 2022–23 State Budget, this school received $12.716 million. A further $551,820 was allocated in 2022.

Funding type

  • Upgrade and Modernisation

Bentleigh Secondary College – indicative site plan

  • Download 'Bentleigh Secondary College – indicative site plan'

Upgrade and Modernisation – Da Vinci Centre

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q3 2019

The above dates are forecast only and subject to change.

About the project

We built a new Da Vinci Centre at the school. The new centre houses science, technology, engineering, arts, and mathematics (STEAM) facilities.

We provided additional basketball facilities, with a new competition-grade, two-court stadium. Other improvements completed included moving relocatable buildings, demolishing others no longer fit for purpose, constructing a new car park and landscaping.​

This project, designed by Haskell was a finalist in the 2019 Victorian School Design Awards.

Funding

In the 2015–16 State Budget, $9.6 million was allocated to the school. Through the School Pride and Sports Fund the school was allocated $3.968 million.

Funding type

  • Upgrade and Modernisation

Updated