- 78A Oakover Rd Preston 3072
Upgrade and Modernisation – Next Stage
Start
Q4 2020Planning
Design
Construction
Finish
Q3 2024
The above dates are forecast only and subject to change.
About the project
We continued to modernise the school. We completed the next stage of the school's master plan, which included building a new gymnasium community hub. The hub houses a competition-grade basketball and netball facility, as well as a canteen and music performance space.
Funding
In the 2020-21 State Budget, the school received $7.172 million.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation
Start
Planning
Design
Construction
Finish
Q4 2019
The above dates are forecast only and subject to change.
About the project
We upgraded and modernised facilities at Bell Primary School, helping the needs of the growing school. The project included a major upgrade and extensions to the underutilised library & library mezzanine spaces. This delivered a new senior school learning hub that is better connected to the existing first floor learning spaces. The project also included a major upgrade to student and staff amenities and improved accessibility.
Funding
In the 2017–18 State Budget Update, $2 million was allocated to the school.
Funding type
- Upgrade and Modernisation