- Robertson Dr Mornington 3931
Minor Capital Works Fund
- StartQ2 2022
- Planning
- Design
- Construction
- FinishQ3 2024
The above dates are forecast only and subject to change.
About the project
We refurbished the school's toilets to improve amenity, cleanliness and hygiene.
Funding
In the 2022–23 State Budget the project received $460,127 from the Minor Capital Works Fund.
Funding type
- Minor Capital Works Fund
Inclusive Schools Fund - Round 7
- StartQ4 2021
- Planning
- Design
- Construction
- FinishQ2 2024
The above dates are forecast only and subject to change.
About the project
We built an inclusive playground, including new play equipment and synthetic rubber.
Funding
In Round 7 of the Inclusive Schools Fund, the project received $200,000.
Funding type
- Inclusive Schools Fund
Inclusive Schools Fund
- Start
- Planning
- Design
- Construction
- FinishQ3 2017
The above dates are forecast only and subject to change.
About the project
We built a joint facility running track to be shared with neighbouring schools.
Funding
In 2016, $200,00 was allocated to the school as part of Round 2 of the Inclusive Schools Fund.
Funding type
- Inclusive Schools Fund
Updated