Upgrade and Modernisation

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q2 2020

The above dates are forecast only and subject to change.

About the project

We upgraded and modernised facilities at the school. We built a multi-purpose hall and equipment room, 2 adjoining new classrooms, as well as a new kitchenette, office and toilets.​​

Funding

In the 2017–18 State Budget, $2 million was allocated to the school.

Funding type

  • Upgrade and Modernisation

Minor Capital Works Fund

  • Start

    Q4 2020
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2022

The above dates are forecast only and subject to change.

About the project

We upgraded the student toilets to improve cleanliness and hygiene.

Funding

In the 2020 Minor Capital Works Fund, the school was allocated $500,000.