Chelsea Primary School

Location
34-44 Argyle Av Chelsea 3196

Upgrade and Modernisation

  • Start

    Q2 2021
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2024

The above dates are forecast only and subject to change.

About the project

We're upgrading and modernising the school. We're building new multipurpose, art and music spaces and toilets.

This ensures students are learning in an environment designed for delivering modern education.

Funding

In the 2021–22 State Budget, the school received $3.889 million.

Funding type

  • Upgrade and Modernisation

Chelsea Primary School - indicative floor plan, community hub

  • Download' Chelsea Primary School - indicative floor plan, community hub'

Inclusive Schools Fund

  • Start

    Q4 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2021

The above dates are forecast only and subject to change.

About the project

We built an all-inclusive oasis space that supports the development of students of all abilities.

Funding

In 2019, $200,000 was allocated to the school in Round 5 of the Inclusive Schools Fund.

Funding type

  • Inclusive Schools Fund

Updated